USCF GMP 12.09 UPS VBS (posted 04-02-2019)
LOJV and the State of Utah appreciate all the interest and efforts made by the subcontractor community. Based the Value Based Selection process and on the most complete RFP response, this scope will be awarded to LPD/Schneider Electrical. USCF GMP 12.09 UPS VBS Scoring Sheet

USCF GMP 12.10 INVERTER VBS (posted 04-02-2019)
LOJV and the State of Utah appreciate all the interest and efforts made by the subcontractor community. Based the Value Based Selection process and on the most complete RFP response, this scope will be awarded to LPD/Schneider. USCF GMP 12.10 INVERTER VBS Scoring Sheet

USCF GMP 12.06 Instrumentation and Controls VBS Scoring Results (posted 2-12-2019)
LOJV and the State of Utah appreciate all the interest and efforts made by the subcontractor community. Per the requirements of the VBS RFP this scope of work will be awarded to Harris Company based on the overall scoring results. USCF GMP 12.06 Instrumentation and Controls VBS Scoring Sheet

USCF VBS Detention Equipment Contractor Scoring Results (posted 11-13-2018)
LOJV and the State of Utah appreciate all the interest and efforts made by the subcontractor community. The scoring committee, using DFCM VBS standards, has determined that CML will be awarded the Detention Equipment scope. USCF VBS Detention Equipment Contractor Scoring Sheet

USCF VBS Security Electronics Contractor Scoring Results (posted 11-13-2018)
LOJV and the State of Utah appreciate all the interest and efforts made by the subcontractor community. The scoring committee, using DFCM VBS standards, has determined that CML will be awarded the Security Electronics scope.USCF VBS Security Electronics Contractor Scoring Sheet

Electrical Substation and Back Up Generation System

USCF Substation RFP Scoring Sheet

Cell RFP (posted 04-25-2018)

USCF Cell RFP Scoring Sheet

USCF Cell Cost Recap

Cell RFP Justification Letter

Haul Road (posted 12-06-2016)

UTAH STATE CORRECTIONAL FACILITY USCF GMP1 Haul Road (PDF)



Central Utah Correctional Facility West One Expansion, Gunnison, UT | Built by Layton Construction

This website exists to enhance collaboration between Layton Okland and subcontractors and suppliers who are or wish to become part of constructing the new Utah State Correctional Facility.

Project Director
Bruce McDonough

General Construction Questions
Dave Whimpey, Senior Project Manager

Bidding / Estimating Questions
Thomas Quam, Senior Estimator

Site Questions
Tom Dalton, Senior Project Manager

Links

New Utah State Correctional Facility website